Sarah: Thanks for coming, everyone. Let's get straight to it. The main goal today is to firm up the timeline for the 'Phoenix' project launch.
John: Right. I've drafted a preliminary schedule based on our last discussion. We're looking at a potential launch in early Q3.
Maria: Q3? That seems a bit aggressive, John. Marketing needs at least six weeks post-development for the campaign.
Sarah: Maria has a point. We need to factor that in. John, can you adjust the schedule to reflect that? Perhaps pushing the development completion date back slightly?
John: I can try. It might impact the initial resource allocation, though. I'll need to review that section.
Maria: While we're discussing schedules, I also need to book my annual health checkup appointment. Does anyone know if Dr. Evans's office has openings next Friday afternoon?
Sarah: I'm not sure about Dr. Evans, but my clinic has some slots available. I can send you the details if you're interested. We should probably finish this project discussion first, though.
John: Agreed. Let's focus here. I'll rework the schedule and circulate it by end of day. We can address any further concerns in our follow-up meeting.
Soal
What might happen if John adjusts the schedule?
Pilihan
- A. Marketing campaign may be delayed.
- B. Resource allocation might be affected. ✓
- C. The launch date will be moved to Q4.
- D. Dr. Evans's office may have openings.
Jawaban
B. Resource allocation might be affected.
Pembahasan
📖 Terjemahan Teks — Para peserta rapat bertujuan untuk memfinalisasi kerangka waktu peluncuran proyek 'Phoenix'. John telah menyusun jadwal tentatif, tetapi Maria menunjukkan bahwa peluncuran di Q3 tampak terlalu agresif karena tim pemasaran membutuhkan setidaknya enam minggu pasca-pengembangan untuk kampanye. Sarah meminta John untuk menyesuaikan jadwal guna memperhitungkan tim pemasaran, mungkin dengan sedikit menunda tanggal penyelesaian pengembangan.
📝 Alasan Jawaban — Meskipun ucapan John terputus pada "initial r" ketika dia mengatakan dia bisa mencoba menyesuaikan jadwal, mengingat Maria berkata "Marketing needs at least six weeks post-development for the campaign", kita dapat menyimpulkan bahwa menunda tanggal penyelesaian pengembangan dapat memengaruhi aktivitas pemasaran. Oleh karena itu, "Resource allocation might be affected" adalah kesimpulan yang paling logis. Perubahan dalam jadwal pengembangan dapat menyebabkan alokasi kembali sumber daya (misalnya, personel, anggaran).
💡 Tips Tes — Di Bagian 3, soal yang mengharuskan Anda menyimpulkan dari konteks percakapan sering kali muncul. Dalam kasus percakapan yang tiba-tiba terputus seperti ini, berlatih menyimpulkan hasil yang paling logis berdasarkan konten percakapan sebelumnya sangatlah penting. Kata-kata seperti "affect" dapat memberikan petunjuk tentang hasil.
📊 Analisis Pilihan Salah — X) Marketing campaign may be delayed. — Maria mengatakan tim pemasaran membutuhkan enam minggu pasca-pengembangan, tetapi dia tidak secara langsung mengatakan "kampanye mungkin tertunda", melainkan berarti jadwal saat ini tidak mencukupi untuk kampanye. X) The launch date will be moved to Q4. — John mengatakan dia bisa mencoba menyesuaikan jadwal, tetapi dia tidak memastikan bahwa itu akan dipindahkan ke Q4. Mungkin hanya penyesuaian kecil dari awal Q3. X) Dr. Evans's office may have openings. — Tidak ada penyebutan tentang Dr. Evans dalam teks. Ini adalah informasi yang sama sekali tidak relevan.