TOEIC Reading Part 7 — Bacaan

Bacaan

Subject: Project Alpha - Schedule Update
From: Emily Chen <echen@grandcorp.com>
To: Project Alpha Team <alpha-team@grandcorp.com>
Date: Monday, October 28, 9:30 AM

Hi Team,

I'm writing to inform everyone that due to unforeseen technical issues with the new software integration, Project Alpha's launch will be slightly delayed. Our original target launch date of November 15th is no longer feasible. We are currently reassessing the timeline and will provide an updated schedule by the end of this week. I appreciate your understanding and continued hard work.

Best regards,
Emily Chen
Project Manager

---Attachment: ProjectAlpha_InitialImpactAssessment.pdf---

Subject: Re: Project Alpha - Schedule Update
From: David Lee <dlee@grandcorp.com>
To: Emily Chen <echen@grandcorp.com>
Date: Monday, October 28, 11:45 AM

Hi Emily,

Thanks for the update. Could you clarify the specific technical issues? Also, will this delay impact the resource allocation for the beta testing phase? My team has already committed significant hours based on the original timeline.

Thanks,
David Lee
Lead Developer

Subject: Re: Project Alpha - Schedule Update
From: Emily Chen <echen@grandcorp.com>
To: David Lee <dlee@grandcorp.com>
Date: Monday, October 28, 1:30 PM

Hi David,

The primary issue stems from compatibility problems between our existing database system and the new analytics module. We're working closely with the vendor to resolve it. Regarding resource allocation, I anticipate we'll need to shift some resources, but I'll confirm the full impact on beta testing by Wednesday. I'll send out a detailed report with revised timelines soon.

Thanks,
Emily Chen

Soal (1)