TOEIC Listening Part 3 — Soalan

Petikan

Man: Okay everyone, thanks for gathering today. Let's talk about the city park renovation project. Sarah, can you start us off with the overall schedule?
Woman 1 (Sarah): Sure. We've outlined a three-phase approach. Phase one, site assessment and initial cleanup, should take about two weeks. Then phase two, actual construction and planting, is estimated for six weeks. Phase three, final touches and opening, will be another two weeks.
Man: That sounds like a reasonable timeframe. What about potential delays? Any major concerns?
Woman 1 (Sarah): Well, the biggest unknown is the weather, especially during the planting phase. Also, we need to coordinate closely with the city council regarding the parking lot maintenance. They handle that, and we need to ensure it's done before we start major landscaping, so it doesn't disrupt access.
Man: Good point. We don't want visitors complaining before we even open. Let's make sure that parking lot maintenance is scheduled at least a week before phase two begins. What’s the budget looking like?
Woman 2 (Maria): The initial budget seems okay, but the cost for new benches and lighting fixtures is a bit higher than anticipated. We might need to look at alternative suppliers or perhaps slightly reduce the scope in phase three if necessary.

Baca petikan penuh →

Soalan

When does the man want the parking lot maintenance to be completed?

Pilihan

  1. A. Before the project begins
  2. B. At least one week before phase two ✓
  3. C. During phase three of the project
  4. D. By the end of the planting phase

Jawapan

B. At least one week before phase two

Penjelasan

📖 Terjemahan petikan — Seorang lelaki mengumpulkan semua orang untuk membincangkan projek pengubahsuaian taman bandar. Sarah memulakan perbincangan mengenai jadual keseluruhan, menganggarkan fasa satu (penilaian tapak dan pembersihan awal) akan mengambil masa kira-kira dua minggu. Kemudian fasa dua (pembinaan dan penanaman sebenar) dianggarkan selama enam minggu, dan fasa tiga (sentuhan akhir dan pembukaan) akan mengambil masa dua minggu lagi. Lelaki itu bertanya tentang potensi kelewatan.
📝 Sebab pilihan ini betul — Jawapan kepada soalan bila lelaki itu mahu penyelenggaraan tempat letak kereta selesai tidak dinyatakan secara eksplisit dalam petikan. Walau bagaimanapun, soalan itu sendiri ialah "When does the man want the parking lot maintenance to be completed?", jadi adalah penting untuk memahami permintaan lelaki itu dengan tepat. Antara pilihan yang diberikan, "At least one week before phase two" (Sekurang-kurangnya satu minggu sebelum fasa dua) kelihatan paling baik mencerminkan kebimbangan lelaki itu mengenai jadual tersebut. (Nota: Soalan dan jawapan dalam teks asal mungkin berbeza daripada ujian mendengar sebenar, dan tafsiran mungkin berbeza bergantung pada niat pencipta soalan.)
💡 Petua semasa ujian — Dalam Part 3, adalah penting untuk mengenal pasti dengan jelas siapa/apa yang ditanya dan bila/mengapa. Tandakan kata kunci utama dalam soalan, dan cari maklumat yang berkaitan dengan kata kunci tersebut dalam petikan.
📊 Analisis pilihan salah — X) Before the project begins — Selesai sebelum projek bermula tidak masuk akal dari konteks. X) During phase three of the project — Selesai semasa fasa tiga juga terlalu lewat atau tidak sesuai. X) By the end of the planting phase — Selesai menjelang akhir fasa penanaman mungkin terlalu awal dan tidak mencerminkan kebimbangan lelaki itu yang lain.