TOEIC 리딩 파트 7 — 문제

지문

Subject: Urgent: Marketing Campaign Launch Update - Project Phoenix
From: Michael Harrison <m.harrison@syntech.com>
To: Sarah Jenkins <s.jenkins@syntech.com>, David Lee <d.lee@syntech.com>, Elena Petrova <e.petrova@syntech.com>
Date: October 23, 10:15 AM

Team,

I regret to inform you that the launch of the Project Phoenix marketing campaign will be slightly delayed. The unforeseen technical issues identified during final testing of the backend integration pose a significant hurdle. Our developers are working around the clock to resolve them, but it’s become clear we won't meet our original November 1st target. I wanted to provide an immediate update before our scheduled meeting this afternoon. Sarah, please coordinate with your team to assess the impact on our promotional materials. David, can you provide an updated timeline for the technical fixes? Elena, please draft a communication plan for our external stakeholders.

Best,
Michael Harrison

---
Subject: Re: Urgent: Marketing Campaign Launch Update - Project Phoenix
From: Sarah Jenkins <s.jenkins@syntech.com>
To: Michael Harrison <m.harrison@syntech.com>
Cc: David Lee <d.lee@syntech.com>, Elena Petrova <e.petrova@syntech.com>
Date: October 23, 10:40 AM

Michael,

Thanks for the heads-up. My team can pivot quickly. We’ll hold off on sending the final proofs to print and adjust the digital assets. I'll have an impact assessment for you by end of day.

Sarah Jenkins

---
Subject: Re: Urgent: Marketing Campaign Launch Update - Project Phoenix
From: David Lee <d.lee@syntech.com>
To: Michael Harrison <m.harrison@syntech.com>
Cc: Sarah Jenkins <s.jenkins@syntech.com>, Elena Petrova <e.petrova@syntech.com>
Date: October 23, 11:05 AM

Michael,

We're looking at an additional 5-7 business days for the backend integration, assuming no further complications. This puts our revised launch window at November 8th-10th. I'll circulate a more detailed report with the specific outstanding issues shortly.

David Lee

---
Subject: Re: Urgent: Marketing Campaign Launch Update - Project Phoenix
From: Elena Petrova <e.petrova@syntech.com>
To: Michael Harrison <m.harrison@syntech.com>
Cc: Sarah Jenkins <s.jenkins@syntech.com>, David Lee <d.lee@syntech.com>
Date: October 23, 11:20 AM

Understood, Michael. I'll prepare a concise statement for our key partners emphasizing the minor scope adjustment and the continued commitment to quality. I'll also draft an internal memo to manage expectations within the company. I'll have initial drafts ready for your review by tomorrow morning.

Elena Petrova

지문 전체 보기 →

문제

How many additional business days are anticipated for the backend integration?

보기

  1. A. 5 to 7 days. ✓
  2. B. 1 to 3 days.
  3. C. 10 to 12 days.
  4. D. Less than 5 days.

정답

A. 5 to 7 days.

해설

📖 지문해석 — 이메일은 Project Phoenix 마케팅 캠페인 출시가 약간 지연될 것임을 알리고 있습니다. 백엔드 통합의 최종 테스트 중 발견된 예상치 못한 기술적 문제가 상당한 장애물을 제시하고 있습니다. 개발팀은 문제를 해결하기 위해 24시간 노력하고 있지만, 원래 마감일을 맞추지 못할 것이 분명해졌습니다.
📝 정답이유 — 질문은 백엔드 통합에 예상되는 추가 업무 일수를 묻고 있습니다. 이메일 본문에서 "it’s become clear we won't meet our original No"와 같은 직접적인 언급은 없지만, 맥락상 예상치 못한 기술 문제로 인해 지연이 발생하며, 이는 복구를 위해 추가적인 시간이 소요됨을 의미합니다. 옵션 중에서 "5 to 7 days"는 일반적으로 기술 문제 해결과 이에 따른 업무 지연에 걸리는 합리적인 시간 범위를 나타내며, 가장 타당한 추정치입니다.
💡 실전팁 — Part 7에서는 명시적 정보 외에 문맥을 통한 추론이 중요합니다. "unforeseen technical issues"와 같은 구문은 지연과 추가 작업 시간을 암시하므로, 이를 보기에 있는 시간 범위와 연결하여 가장 가능성 높은 답을 선택하세요.
📊 오답분석 — X) 1 to 3 days. — 너무 짧은 시간으로, 심각한 기술 문제 해결 및 출시 지연 복구에 부족할 수 있습니다. X) 10 to 12 days. — 과도하게 긴 시간으로, 특별한 언급 없이 이 정도의 지연은 흔하지 않습니다. X) Less than 5 days. — 4일 이하의 시간으로, "5 to 7 days"보다 더 짧아 문제 해결에 충분하지 않을 가능성이 높습니다.