TOEIC 리스닝 파트 3 — 문제

지문

Woman: Thanks for coming, everyone. Let's start by reviewing the project timeline. We're aiming for a launch in Q4.
Man 1: Right. I wanted to confirm the key milestones. Specifically, when are the development and testing phases scheduled to conclude?
Woman: Development is slated for completion by mid-August, with testing to follow for three weeks. This gives us ample time for the data backup procedure before the final rollout.
Man 2: That sounds reasonable. Have we allocated sufficient resources for the User Acceptance Testing phase? It always takes longer than expected.
Woman: We've factored in a buffer of 10% for unforeseen issues. Also, regarding the data backup procedure, please ensure all team members have access to the secure server location by the end of this week.
Man 1: Understood. So, the target launch date is still the first week of November?
Woman: That's the plan. Let's circle back on the budget details next.

지문 전체 보기 →

문제

What does Man 2 ask about regarding the UAT phase?

보기

  1. A. The duration of the phase.
  2. B. The team members involved.
  3. C. The allocated resources. ✓
  4. D. The potential risks.

정답

C. The allocated resources.

해설

📖 지문해석 — Man 2는 사용자 수용 테스트(UAT) 단계에 대해 질문하며, 예상보다 시간이 더 오래 걸리기 때문에 충분한 자원이 할당되었는지 확인하고 싶어 합니다.
📝 정답이유 — Man 2는 "Have we allocated sufficient resources for the User Acceptance Testing phase?"라고 직접적으로 물어봅니다. 'sufficient resources'는 '할당된 자원'이라는 뜻으로, 3번 선택지 'The allocated resources'와 일치합니다.
💡 실전팁 — Part 3에서는 질문자의 의도를 파악하는 것이 중요합니다. Man 2의 질문에서 'allocated resources'라는 핵심 어휘가 나오므로, 이와 직접적으로 연결되는 선택지를 찾아야 합니다.
📊 오답분석 — X) The duration of the phase. — Man 2는 UAT 기간이 더 오래 걸릴 수 있다고 언급했지만, 직접적으로 기간 자체에 대해 묻지는 않았습니다. X) The team members involved. — 대화 어디에도 팀원에 대한 언급은 없습니다. X) The potential risks. — 위험 요소에 대한 언급은 없었으며, 자원 할당에 대한 질문입니다.