TOEIC 閱讀 Part 7 — 題目
段落
Subject: Update: Project Phoenix Timeline Adjustment
Hi Team,
I'm writing to provide a crucial update regarding Project Phoenix. Unfortunately, we're facing an unavoidable delay. The primary reason stems from the unexpected hold-up in the shipment of the specialized micro-processing unit, which is integral to the system's core functionality. Our supplier, TechSolutions Inc., has notified us of a logistical issue on their end, pushing the delivery date back by approximately two weeks. We were initially scheduled to receive it by October 25th, but the new estimated arrival is November 8th.
This delay inevitably impacts our integration and testing phases. Consequently, the projected launch date will be pushed back from December 1st to December 15th. I understand this is frustrating news, and I want to assure you that we are exploring all avenues to mitigate further delays and expedite the remaining tasks once the unit arrives. We've also paused work on the user interface redesign for the sightseeing tour booking portal, as it relies heavily on the finalized specifications of this unit.
I've scheduled an all-hands meeting for tomorrow, October 18th, at 10:00 AM PST to discuss the revised timeline and potential contingency plans. Please come prepared with any questions or suggestions.
Best regards,
Maria Garcia
Project Manager
---
Subject: Re: Update: Project Phoenix Timeline Adjustment
Hi Maria,
Thanks for the update. This is indeed a setback. Have we considered alternative suppliers for the micro-processing unit, even as a backup?
Also, regarding the sightseeing tour booking portal, does this delay affect the upcoming marketing campaign that was scheduled to coincide with the initial launch?
Regards,
David Chen
Lead Developer
---
Subject: Re: Update: Project Phoenix Timeline Adjustment
Hi David,
Good questions. We did inquire about alternative suppliers early on, but TechSolutions was the only one capable of providing the exact specifications required within a reasonable timeframe. At this point, switching suppliers would likely cause an even greater delay.
Regarding the marketing campaign for the sightseeing tour booking portal, yes, it will need to be rescheduled. We'll need to align it with the new December 15th launch date. I'll coordinate with the marketing team shortly.
Let's focus on the mitigation strategies for the technical tasks during the all-hands meeting tomorrow.
Best,
Maria
題目
What is the new estimated launch date for Project Phoenix?
選項
- A. October 25th
- B. November 8th
- C. December 1st
- D. December 15th ✓
正確答案
D. December 15th
解析
📖 文章翻譯 — 主旨:專案鳳凰時間表更新通知
各位團隊成員您好:
我寫這封信是為了提供「專案鳳凰」的關鍵更新。很可惜,我們面臨了無法避免的延遲。主要原因是收到了一個特殊微處理器的貨運延誤,而該零件是系統核心功能不可或缺的。我們的供應商 TechSolutions Inc. 已通知我們他們端遇到了物流問題,這將使交貨日期延後約兩週。我們原定於 10 月 25 日收到,但新的預計到達日期是 11 月 8 日。
📝 答案解析 — 正確答案是「11 月 8 日」。文章中明確提到:「我們原定於 10 月 25 日收到,但新的預計到達日期是 11 月 8 日。」這直接回答了新預計發布日期為何。
💡 應試技巧 — 尋找表示「新」、「預計」、「更新」或「延後」的關鍵字,這些詞語通常指向問題所詢問的變動資訊。
📊 錯誤選項分析 —
X) 10 月 25 日 — 這是專案「原定」的收到日期,而非更新後的預計日期。
X) 12 月 1 日 — 文章中未提及此日期,與供應商通知的延誤無關。
X) 12 月 15 日 — 文章中未提及此日期,與供應商通知的延誤無關。
相關題目
- Where should applicants send their documents?
- What quality of the coffee maker is highlighted?
- Which statement best describes the reviewer's overall recommendation?
- Who is eligible to participate in 'Innovate & Grow'?
- Who is the Everest Backpack Pro particularly recommended for?
- Which service is NOT listed as a potential assistance provided by the concierge