TOEIC 리딩 파트 7 — 문제
지문
Subject: Update: Project Phoenix Timeline Adjustment
Hi Team,
I'm writing to provide a crucial update regarding Project Phoenix. Unfortunately, we're facing an unavoidable delay. The primary reason stems from the unexpected hold-up in the shipment of the specialized micro-processing unit, which is integral to the system's core functionality. Our supplier, TechSolutions Inc., has notified us of a logistical issue on their end, pushing the delivery date back by approximately two weeks. We were initially scheduled to receive it by October 25th, but the new estimated arrival is November 8th.
This delay inevitably impacts our integration and testing phases. Consequently, the projected launch date will be pushed back from December 1st to December 15th. I understand this is frustrating news, and I want to assure you that we are exploring all avenues to mitigate further delays and expedite the remaining tasks once the unit arrives. We've also paused work on the user interface redesign for the sightseeing tour booking portal, as it relies heavily on the finalized specifications of this unit.
I've scheduled an all-hands meeting for tomorrow, October 18th, at 10:00 AM PST to discuss the revised timeline and potential contingency plans. Please come prepared with any questions or suggestions.
Best regards,
Maria Garcia
Project Manager
---
Subject: Re: Update: Project Phoenix Timeline Adjustment
Hi Maria,
Thanks for the update. This is indeed a setback. Have we considered alternative suppliers for the micro-processing unit, even as a backup?
Also, regarding the sightseeing tour booking portal, does this delay affect the upcoming marketing campaign that was scheduled to coincide with the initial launch?
Regards,
David Chen
Lead Developer
---
Subject: Re: Update: Project Phoenix Timeline Adjustment
Hi David,
Good questions. We did inquire about alternative suppliers early on, but TechSolutions was the only one capable of providing the exact specifications required within a reasonable timeframe. At this point, switching suppliers would likely cause an even greater delay.
Regarding the marketing campaign for the sightseeing tour booking portal, yes, it will need to be rescheduled. We'll need to align it with the new December 15th launch date. I'll coordinate with the marketing team shortly.
Let's focus on the mitigation strategies for the technical tasks during the all-hands meeting tomorrow.
Best,
Maria
문제
What is the new estimated launch date for Project Phoenix?
보기
- A. October 25th
- B. November 8th
- C. December 1st
- D. December 15th ✓
정답
D. December 15th
해설
📖 지문해석 — 이메일은 팀에게 Project Phoenix에 대한 중요한 업데이트를 전달합니다. 마이크로프로세싱 단위의 배송 지연으로 인해 프로젝트에 불가피한 지연이 발생했으며, 이는 원래 10월 25일에서 11월 8일로 배송일을 늦추었습니다.
📝 정답이유 — 문제에서 새로운 예상 출시일을 묻고 있습니다. 본문에는 "the new estimated arrival is November 8th"라는 문구가 명시되어 있어, 지연 후의 새로운 도착 예정일이 11월 8일임을 명확히 나타냅니다.
💡 실전팁 — 날짜 관련 질문에서는 'new', 'revised', 'estimated', 'scheduled'와 같은 키워드를 찾아 시간 관련 정보를 집중적으로 확인하세요.
📊 오답분석 — X) October 25th — 이것은 초기 배송 예정일이었으나, 지연으로 인해 변경되었습니다. X) December 1st — 이 날짜는 본문에 언급되지 않은 가상의 날짜입니다. X) December 15th — 이 날짜 역시 본문 내용과 관련이 없는 가상의 날짜입니다.
관련 문제
- Where should applicants send their documents?
- What quality of the coffee maker is highlighted?
- Which statement best describes the reviewer's overall recommendation?
- Who is eligible to participate in 'Innovate & Grow'?
- Who is the Everest Backpack Pro particularly recommended for?
- Which service is NOT listed as a potential assistance provided by the concierge