TOEIC 聽力 Part 3 — 題目
段落
Woman: Thanks for coming, everyone. Let's start by reviewing the project timeline. We're aiming for a launch in Q4.
Man 1: Right. I wanted to confirm the key milestones. Specifically, when are the development and testing phases scheduled to conclude?
Woman: Development is slated for completion by mid-August, with testing to follow for three weeks. This gives us ample time for the data backup procedure before the final rollout.
Man 2: That sounds reasonable. Have we allocated sufficient resources for the User Acceptance Testing phase? It always takes longer than expected.
Woman: We've factored in a buffer of 10% for unforeseen issues. Also, regarding the data backup procedure, please ensure all team members have access to the secure server location by the end of this week.
Man 1: Understood. So, the target launch date is still the first week of November?
Woman: That's the plan. Let's circle back on the budget details next.
題目
What does Man 2 ask about regarding the UAT phase?
選項
- A. The duration of the phase.
- B. The team members involved.
- C. The allocated resources. ✓
- D. The potential risks.
正確答案
C. The allocated resources.
解析
📖 文章翻譯 — 女:謝謝大家來。我們就從檢視專案時程開始吧。我們的目標是在第四季推出。
男1:對。我想確認一下關鍵里程碑。具體來說,開發和測試階段預計何時結束?
女:開發預計在八月中完成,測試會接著進行三週。這樣我們就有充裕的時間執行資料備份程序,然後再進行最終上線。
男2:聽起來很合理。我們有為使用者驗收測試(UAT)階段分配足夠的資源嗎?它總是比預期的時間來得長。
女:我們已經考慮了
選項:["該階段的持續時間。","涉及的團隊成員。","分配的資源。","潛在的風險。"]
📝 答案解析 — 男2明確詢問「Have we allocated sufficient resources for the User Acceptance Testing phase?」(我們有為使用者驗收測試階段分配足夠的資源嗎?),這直接對應了選項「The allocated resources」(分配的資源)。他對UAT的擔憂「It always takes longer than expected.」(它總是比預期的時間來得長)也暗示了他對資源與時程的關切。
💡 應試技巧 — 當聽到對話中某一方提出一個關於特定階段(如UAT)的疑問,特別是關於「資源」(resources)、「時間」(time)、「人員」(staff)等關鍵字時,應預期考點會圍繞該階段的相關要素。
📊 錯誤選項分析 — X) 該階段的持續時間 — 雖然男2提到UAT「總是比預期的時間來得長」,但他問的重點是「資源」是否充足,而不是時間長短本身。X) 涉及的團隊成員 — 對話中並未提及UAT階段具體的團隊成員。X) 潛在的風險 — 男2的提問是關於資源分配,而不是討論UAT可能面臨的風險。