Woman: Thanks for coming, everyone. Let's start by reviewing the project timeline. We're aiming for a launch in Q4.
Man 1: Right. I wanted to confirm the key milestones. Specifically, when are the development and testing phases scheduled to conclude?
Woman: Development is slated for completion by mid-August, with testing to follow for three weeks. This gives us ample time for the data backup procedure before the final rollout.
Man 2: That sounds reasonable. Have we allocated sufficient resources for the User Acceptance Testing phase? It always takes longer than expected.
Woman: We've factored in a buffer of 10% for unforeseen issues. Also, regarding the data backup procedure, please ensure all team members have access to the secure server location by the end of this week.
Man 1: Understood. So, the target launch date is still the first week of November?
Woman: That's the plan. Let's circle back on the budget details next.
題目
What will be discussed next?
選項
- A. The implications of the data backup procedure.
- B. The details of the project budget. ✓
- C. The marketing campaign strategy.
- D. The completion of the testing phase.
正確答案
B. The details of the project budget.
解析
📖 文章翻譯 —
女:謝謝大家前來。我們就從審視專案時程表開始。我們的目標是在第四季推出。
男1:好的。我想確認一下關鍵的里程碑。具體來說,開發及測試階段預計���時結束?
女:開發案預計在八月中旬完成,隨後進行為期三週的測試。這樣我們在最終上線前,就有充裕的時間進行資料備份程序。
男2:聽起來還算合理。我們是否為使用者驗收測試階段分配了足夠的資源?這部分總是比預期花費更多時間。
女:我們已經考量進去了
📝 答案解析 —
根據對話,開發案預計在八月中旬完成,測試階段將隨後進行三週。男2接著問到使用者驗收測試(UAT)的資源分配,而女方回應「我們已經考量進去了」,這緊接著就會討論到UAT的細節,其中就包含了測試階段的完成狀況。因此,下一個討論主題很可能是關於測試階段的進度與細節。
💡 應試技巧 —
聽取對話時,注意說話者提到的下一個階段或議題的關鍵詞,並預測對話的自然延續方向。當問到資源分配時,通常會接續討論該階段的具體規劃或潛在問題。
📊 錯誤選項分析 —
X) 資料備份程序的影響 — 雖然有提到資料備份,但它被視為測試完成後的步驟,不是下一個主要討論點。
X) 專案預算細節 — 對話中完全沒有提及預算。
X) 行銷活動策略 — 對話專注於專案開發與測試時程,未觸及市場推廣。