TOEIC 聽力 Part 3 — 題目

段落

Sarah: Thanks for coming, everyone. Let's get straight to it. The main goal today is to firm up the timeline for the 'Phoenix' project launch.
John: Right. I've drafted a preliminary schedule based on our last discussion. We're looking at a potential launch in early Q3.
Maria: Q3? That seems a bit aggressive, John. Marketing needs at least six weeks post-development for the campaign.
Sarah: Maria has a point. We need to factor that in. John, can you adjust the schedule to reflect that? Perhaps pushing the development completion date back slightly?
John: I can try. It might impact the initial resource allocation, though. I'll need to review that section.
Maria: While we're discussing schedules, I also need to book my annual health checkup appointment. Does anyone know if Dr. Evans's office has openings next Friday afternoon?
Sarah: I'm not sure about Dr. Evans, but my clinic has some slots available. I can send you the details if you're interested. We should probably finish this project discussion first, though.
John: Agreed. Let's focus here. I'll rework the schedule and circulate it by end of day. We can address any further concerns in our follow-up meeting.

閱讀完整段落 →

題目

Why does Maria think the proposed timeline is aggressive?

選項

  1. A. It doesn't account for marketing campaign duration. ✓
  2. B. It doesn't allow enough time for development.
  3. C. It conflicts with other project deadlines.
  4. D. It hasn't been approved by management.

正確答案

A. It doesn't account for marketing campaign duration.

解析

📖 文章翻譯 — Sarah:謝謝大家今天來。我們直接開始。今天的主要目標是確定「Phoenix」專案發布的最終時間表。John:好的。我根據上次的討論草擬了一份初步日程。我們預計在第三季初發布。Maria:第三季?John,這看起來有點趕。行銷活動在開發完成後還需要至少六週的時間來準備。Sarah:Maria 說得對。我們必須將這一點考慮進去。John,你能否調整日程以反映這一點?也許將開發完成日期稍微往後推?John:我試試看。這可能會影響最初的...
📝 答案解析 — 正確答案是「它沒有考慮到行銷活動的持續時間」。Maria 明確表示:「行銷需要至少六週的時間來準備活動」,並且認為 Q3 的發布時間「有點趕」,這直接表明了時間表的問題在於未能涵蓋行銷所需的時間。
💡 應試技巧 — 聽到表示不確定或質疑語氣的詞語(如 "seems a bit aggressive", "has a point", "Can you adjust...?"),要特別留意說話者提出質疑的原因,這通常是答案的關鍵線索。
📊 錯誤選項分析 — X) 它沒有為開發提供足夠的時間 —原文並未提及開發時間不足,而是行銷時間不足。 X) 它與其他專案的截止日期衝突 — 文章中沒有提及與其他專案的衝突。 X) 管理層尚未批准 — 文章中沒有提到任何關於管理層批准的資訊。