TOEIC リスニング パート 3 — 問題

パッセージ

Woman: Thanks for coming, everyone. Let's start by reviewing the project timeline. We're aiming for a launch in Q4.
Man 1: Right. I wanted to confirm the key milestones. Specifically, when are the development and testing phases scheduled to conclude?
Woman: Development is slated for completion by mid-August, with testing to follow for three weeks. This gives us ample time for the data backup procedure before the final rollout.
Man 2: That sounds reasonable. Have we allocated sufficient resources for the User Acceptance Testing phase? It always takes longer than expected.
Woman: We've factored in a buffer of 10% for unforeseen issues. Also, regarding the data backup procedure, please ensure all team members have access to the secure server location by the end of this week.
Man 1: Understood. So, the target launch date is still the first week of November?
Woman: That's the plan. Let's circle back on the budget details next.

パッセージ全文を読む →

問題

What does Man 2 ask about regarding the UAT phase?

選択肢

  1. A. The duration of the phase.
  2. B. The team members involved.
  3. C. The allocated resources. ✓
  4. D. The potential risks.

正解

C. The allocated resources.

解説

📖 本文の和訳 — 女性はプロジェクトのタイムラインのレビューを開始しますが、男性1は開発およびテストフェーズがいつ終了するかを尋ねます。女性は開発が8月中旬に完了し、その後に3週間のテストが行われると答えます。男性2は、ユーザー受け入れテスト(UAT)フェーズに十分なリソースが割り当てられているかを確認します。
📝 正解理由 — 男性2は「Have we allocated sufficient resources for the User Acceptance Testing phase?」と直接尋ねており、これは「ユーザー受け入れテスト(UAT)フェーズに十分なリソースが割り当てられているか?」という意味です。したがって、選択肢「The allocated resources」(割り当てられたリソース)が正解となります。
💡 実践的アドバイス — 会話の中で「resources」や「allocate」といったキーワードが出てきたら、それと直接関連する質問や選択肢に注目しましょう。
📊 不正解の選択肢の分析 — X) The duration of the phase. — 男性2はUATに時間がかかると言及しましたが、期間そのものについて質問したわけではありません。X) The team members involved. — 会話の中でチームメンバーに関する言及はありませんでした。X) The potential risks. — リスクではなく、リソースの割り当てについて尋ねています。