Sarah: Thanks for coming, everyone. Let's get straight to it. The main goal today is to firm up the timeline for the 'Phoenix' project launch.
John: Right. I've drafted a preliminary schedule based on our last discussion. We're looking at a potential launch in early Q3.
Maria: Q3? That seems a bit aggressive, John. Marketing needs at least six weeks post-development for the campaign.
Sarah: Maria has a point. We need to factor that in. John, can you adjust the schedule to reflect that? Perhaps pushing the development completion date back slightly?
John: I can try. It might impact the initial resource allocation, though. I'll need to review that section.
Maria: While we're discussing schedules, I also need to book my annual health checkup appointment. Does anyone know if Dr. Evans's office has openings next Friday afternoon?
Sarah: I'm not sure about Dr. Evans, but my clinic has some slots available. I can send you the details if you're interested. We should probably finish this project discussion first, though.
John: Agreed. Let's focus here. I'll rework the schedule and circulate it by end of day. We can address any further concerns in our follow-up meeting.

パッセージ全文を読む →

問題

Why does Maria think the proposed timeline is aggressive?

選択肢

  1. A. It doesn't account for marketing campaign duration. ✓
  2. B. It doesn't allow enough time for development.
  3. C. It conflicts with other project deadlines.
  4. D. It hasn't been approved by management.

正解

A. It doesn't account for marketing campaign duration.

解説

📖 本文の和訳 — Sarahは「Phoenix」プロジェクトのローンチスケジュールを確定するために会議を招集し、Johnは前回の議論に基づいた暫定スケジュールを提示し、第3四半期初頭のローンチを提案します。Mariaは、このスケジュールは少しアグレッシブすぎると考え、マーケティングキャンペーンには開発完了後、最低6週間が必要だと指摘します。
📝 回答理由 — Mariaは、Johnが提示したスケジュールについて「Q3? That seems a bit aggressive, John.」と述べています。その理由は、直後の「Marketing needs at least six weeks post-development for the campaign.」という説明から分かります。つまり、マーケティングキャンペーン期間が考慮されていないため、スケジュールがタイトだと彼女は考えているのです。
💡 試験対策 — Part 3/4では、話し手の反対意見や懸念事項がしばしば正解の根拠となります。「aggressive」、「difficult」、「too soon」、「problem」、「issue」といった単語に注意深く耳を傾け、否定的なニュアンスを把握しましょう。
📊 不正解選択肢の分析 —
X) It doesn't allow enough time for development. — 開発期間の不足については、本文で言及されていません。Mariaはマーケティング期間を問題視しました。
X) It conflicts with other project deadlines. — 他のプロジェクトの締め切りとの競合については、言及されていません。
X) It hasn't been approved by management. — 経営陣の承認の有無については議論されていません。