TOEIC リスニング パート 3 — 問題
パッセージ
Sarah: Thanks for coming, everyone. Let's get straight to it. The main goal today is to firm up the timeline for the 'Phoenix' project launch.
John: Right. I've drafted a preliminary schedule based on our last discussion. We're looking at a potential launch in early Q3.
Maria: Q3? That seems a bit aggressive, John. Marketing needs at least six weeks post-development for the campaign.
Sarah: Maria has a point. We need to factor that in. John, can you adjust the schedule to reflect that? Perhaps pushing the development completion date back slightly?
John: I can try. It might impact the initial resource allocation, though. I'll need to review that section.
Maria: While we're discussing schedules, I also need to book my annual health checkup appointment. Does anyone know if Dr. Evans's office has openings next Friday afternoon?
Sarah: I'm not sure about Dr. Evans, but my clinic has some slots available. I can send you the details if you're interested. We should probably finish this project discussion first, though.
John: Agreed. Let's focus here. I'll rework the schedule and circulate it by end of day. We can address any further concerns in our follow-up meeting.
問題
Why does Maria think the proposed timeline is aggressive?
選択肢
- A. It doesn't account for marketing campaign duration. ✓
- B. It doesn't allow enough time for development.
- C. It conflicts with other project deadlines.
- D. It hasn't been approved by management.
正解
A. It doesn't account for marketing campaign duration.
解説
📖 本文の和訳 — Sarahは「Phoenix」プロジェクトのローンチスケジュールを確定するために会議を招集し、Johnは前回の議論に基づいた暫定スケジュールを提示し、第3四半期初頭のローンチを提案します。Mariaは、このスケジュールは少しアグレッシブすぎると考え、マーケティングキャンペーンには開発完了後、最低6週間が必要だと指摘します。
📝 回答理由 — Mariaは、Johnが提示したスケジュールについて「Q3? That seems a bit aggressive, John.」と述べています。その理由は、直後の「Marketing needs at least six weeks post-development for the campaign.」という説明から分かります。つまり、マーケティングキャンペーン期間が考慮されていないため、スケジュールがタイトだと彼女は考えているのです。
💡 試験対策 — Part 3/4では、話し手の反対意見や懸念事項がしばしば正解の根拠となります。「aggressive」、「difficult」、「too soon」、「problem」、「issue」といった単語に注意深く耳を傾け、否定的なニュアンスを把握しましょう。
📊 不正解選択肢の分析 —
X) It doesn't allow enough time for development. — 開発期間の不足については、本文で言及されていません。Mariaはマーケティング期間を問題視しました。
X) It conflicts with other project deadlines. — 他のプロジェクトの締め切りとの競合については、言及されていません。
X) It hasn't been approved by management. — 経営陣の承認の有無については議論されていません。