TOEIC リスニング パート 3 — 問題

パッセージ

Mandy: So, regarding the Q3 initiative, I think we'll need to extend the timeline for phase two. There have been some unexpected delays with vendor approvals.
Paul: I'm not surprised. Getting all those external stakeholders aligned always takes longer than anticipated. What's your revised projection?
Maria: And what about resource allocation? Will this push impact our availability for the Q4 launch?
Mandy: Good point, Maria. We'll need to re-evaluate our internal team's bandwidth. Paul, can you draft an updated Gantt chart by end of day?
Paul: Absolutely. I'll factor in a more realistic buffer this time.

パッセージ全文を読む →

問題

Why does Mandy suggest extending the timeline?

選択肢

  1. A. Vendor approval process has been slow. ✓
  2. B. The team is short-staffed for the project.
  3. C. There are issues with the project's budget.
  4. D. A new client has requested additional features.

正解

A. Vendor approval process has been slow.

解説

📖 文の翻訳 — Mandyは、第3四半期のイニシアチブについて、フェーズ2のタイムラインを延長する必要があると述べており、ベンダーの承認に予期せぬ遅延があったためです。Paulは驚いておらず、Mariaはそれが第4四半期のローンチの利用可能性に影響するかどうかを尋ねます。
📝 回答理由 — Mandyがタイムラインの延長を提案する理由は、明確に「vendor approvals(ベンダーの承認)」における「unexpected delays(予期せぬ遅延)」があったと述べられているためです。これは、正解の選択肢「Vendor approval process has been slow.(ベンダーの承認プロセスが遅い)」に直接結びつきます。
💡 実践的ヒント — パート3では、話し手がどのような問題点を指摘し、それに対する解決策(締め切りの延長など)を提案しているのか、文脈を把握することが重要です。「because」「due to」「the reason is」のような理由を示す表現に注目しましょう。
📊 不正解選択肢の分析 —
X) The team is short-staffed for the project. — チームの人員不足については、本文中で言及されていません。
X) There are issues with the project's budget. — プロジェクトの予算に関する問題については、一切触れられていません。
X) A new client has requested additional features. — 新しいクライアントや機能追加のリクエストについては、言及されていません。

関連問題